2018 Sanitary Sewer Construction Updates

LAST UPDATED OCTOBER 17, 2018

Work will continue on Pheasant Ridge Road toward S. Old Rand Road, cutting off access for vehicles from some driveways and limiting water usage for some a few residences. Insituform may be knocking on doors to inform residents of more specific needs along their home frontage. Please see the attached map for parking requests and homes that may be affected with limited water usage.

The contractor will not be working Friday, October 19.

Anticipate impacts to South Old Rand Road at Pheasant Ridge Road for 2-4 days next week.

pic Oct 18

Note – work times and locations are subject to change with little to no notice due to weather, equipment, or other reasons.

PROJECT SUMMARY:  As part of ongoing efforts to extend the life of our aging infrastructure, the Village has contracted with Insituform Technologies USA to install cured-in-place pipe (CIPP) lining in large diameter sanitary sewers in your neighborhood.  This process allows for the trenchless installation of a protective pipe liner with limited ground disturbance to the surrounding area.

For this work, the contractor will be accessing the manholes located along streets and in the public utility easements in the area.  These manholes will be accessed for cleaning prior to the lining, then once again for lining activities, and finally for inspection.  You may notice temporary piping and cables laid between manholes during construction operations or overnight between operations.  If piping is laid across driveways or streets, Insituform will be providing access via temporary ramps for vehicles as needed.  

Typically, each section of sewer to be lined will require up to twelve (12) hours to complete, generally between the hours of 7 am & 7 pm.  During this time, the sewer connection to some homes will be sealed off.  Homeowners will be asked to make limited use of toilet facilities and refrain from doing laundry until the service connection can be reestablished.  Additional precautions residents can take during the period of service interruption include keeping toilet lids down and pouring 1-2 cups of water into basement floor drains to keep any odors from entering the home (this recommendation can be done regularly).  

Manhole access will be intermittent as construction activities progress.  The contractor, Insituform Technologies USA and/or the Construction Manager will attempt to contact you in person before to accessing the easements through backyards (if necessary).  Prior to limited water usage period, affected homes will receive a white door hanger informing of the date and times of service interruption. (If work is canceled for that date a red door hanger will notify homeowners of the cancellation).

Contact Manhard Engineering Construction Coordinator Andrea Larson at (847) 325-7310 for specific information or needs regarding this project.

LocationMap

Frequently Asked Questions on the Sanitary Sewer Lining Project is available here.

WORK SCHEDULED FOR OCTOBER 18 (THURSDAY)

Work will continue on Pheasant Ridge Drive, cutting off access for vehicles from some driveways and limiting water usage for some a few residences. Please see the attached map for parking requests and homes that may be affected with limited water usage.

PLEASE PARK VEHICLES ON THE STREET DURING THE DATES POSTED. This work will be coordinated with the Police Department to allow residents to park overnight during work dates. LIMITED WATER USAGE WILL BE IN EFFECT FOR HOMES RECEIVING DOOR HANGERS (day before work is starting). Please see the map below for additional information.

Residents requested to be out of driveways on THURSDAY, October 18 by 7am:

545, 525, 515 Pheasant Ridge Drive.

Homes affected with limited water usage are requested to not perform activities that require large amounts of water usage (running the dishwasher, clothes washer, or long showers).

pic Oct 18

WORK SCHEDULED FOR OCTOBER 22 (MONDAY):

Work will continue on Pheasant Ridge Drive and along S. Old Rand Road. Select residents along Beechwood Drive may be contacted by the contractor as hoses will be laid along sideyards and under some fences. Few residents may be cut off from vehicular access to driveways. Limited water usage will affect a few residences as well. Please see the attached map for parking requests and homes that may be affected with limited water usage.

PLEASE PARK VEHICLES ON THE STREET DURING THE DATES POSTED. This work will be coordinated with the Police Department to allow residents to park overnight during work dates. LIMITED WATER USAGE WILL BE IN EFFECT FOR HOMES RECEIVING DOOR HANGERS (day before work is starting). Please see the map below for additional information.

Residents requested to be out of driveways on MONDAY, October 22 by 7am:

525, 515, 481, 485 Pheasant Ridge Drive.

Homes affected with limited water usage are requested to not perform activities that require large amounts of water usage (running the dishwasher, clothes washer, or long showers).

pic Oct 22