Buffalo Creek Lift Station Replacement

Throughout the Summer the Village will be replacing the Buffalo Creek Lift Station located on Buffalo Creek Drive. The construction will involve closing Buffalo Creek Drive to through traffic for the duration of the construction and limit access to those who reside on Buffalo Creek Drive. Please see the documents on the right for more information.

During the week of September 17, 2018, crews completed the installation of a majority of the mechanicals and rough-graded the area around the lift station and drive. The concrete slabs were poured for the lift station and cabinet, leaving the remaining electrical work, and installed the control cabinet. We are currently scheduled for the station to go live on September 26 weather permitting.